The exam at a glance
- Computer-based, multiple choice with four answer choices and one best answer.
- 3½ hours for each exam, trade and Law & Business (CSLB exam FAQ). CSLB does not publish the number of questions or the passing score.
- Closed book: no reference materials; a calculator is provided.
- Most applicants also take the Law & Business exam (included free with every trade exam here).
Source: CSLB C-33 study guide. Always confirm details with CSLB before test day.
What's on the exam
- Surface Preparation & Repair30%
- Planning & Estimating28%
- Application of Paint & Finishes21%
- Safety21%
Section weights from the official exam outline. Bigger sections are worth more points, so study them first.
A 4-step study plan
- Take a baseline test. Answer a full mock exam before studying so you know where you stand in each section.
- Study by weight, then by weakness. Start with Surface Preparation & Repair (30%), Planning & Estimating (28%), Application of Paint & Finishes (21%), then move to whichever sections scored lowest on your baseline.
- Learn the rule, not just the answer. For every miss, read the explanation and the code section or statute it cites; on test day you'll need to know these references well.
- Repeat mock exams until you're consistently at 80% or more, which gives you a cushion above the passing score. Retake the questions you missed until they stick.
Key rules to know, by section
A few of the facts that come up in each section, with the answer and the source. The full course has 1,347 questions with explanations.
Surface Preparation & Repair 30% of the exam · 69 practice questions
- A tape test (ASTM D3359) on existing paint checks? Adhesion of the existing coating. The tape test (ASTM D3359) checks adhesion: cut through the coating, press tape firmly over it, and pull it off. If paint comes off with the tape, the existing coating is not sound enough to paint over and must be removed.
- Nail holes in wood trim to be painted are filled with? Wood filler or spackle, then sanded and spot-primed. Fill nail holes in paint-grade trim with wood filler or spackle, sand flush, and spot-prime the filler before topcoating so it doesn't absorb paint differently and show.
- Under EPA RRP, the work area must be cleaned with? HEPA vacuums and wet wiping, followed by cleaning verification. Rule (40 CFR §745.85(a)(5) and (b)): after the work, the area is cleaned with HEPA vacuums and wet wiping or wet mopping until no dust or debris remains, then a certified renovator performs cleaning verification. 40 CFR §745.85(a)(5) (cleaning the work area) ↗
Planning & Estimating 28% of the exam · 22 practice questions
- A finish schedule on the plans tells the painter? Which coating system and color goes on each surface. The finish schedule (often with a room finish schedule) lists, for each surface, the coating system (primer and finish coats), product, sheen and color. The painter follows it together with the specifications.
- Which takes the most labor per square foot, all else equal? Detailed trim, doors and windows. Labor depends on cutting in and detail, not just area. Trim, doors, windows and other detail work need careful brushing and masking, so they take the most labor per square foot.
- Before renovation in pre-1978 housing, the EPA requires giving occupants the? Renovate Right pamphlet. Rule (40 CFR §745.84(a)): before renovating pre-1978 housing, the firm must give the owner (and occupants) EPA's Renovate Right pamphlet no more than 60 days before work begins, and get a written acknowledgment or proof of delivery. 40 CFR §745.84(a) (Renovate Right pamphlet) ↗
Application of Paint & Finishes 21% of the exam · 46 practice questions
- Latex paint should generally not be applied when temperatures are below about? 50°F (or the label minimum). Most latex paints need air and surface temperatures of at least about 50°F during application and drying, though some low-temperature formulas allow 35°F. Always follow the label's minimum.
- Two-component epoxy or urethane coatings must be? Mixed in the correct ratio and used within their pot life. Two-component epoxy and urethane coatings cure by a chemical reaction. They must be mixed in exactly the manufacturer's ratio and used within the pot life, after which the mix thickens and can't be applied properly.
- Spraying on a windy day outdoors can cause? Overspray drift onto cars and property. Wind carries spray mist far from the work area, coating cars, buildings and plants with overspray. On windy days, shield and mask heavily, switch to brush and roller, or reschedule.
Safety 21% of the exam · 45 practice questions
- Two-component polyurethanes containing isocyanates when sprayed require? Supplied-air respiratory protection or as the SDS specifies. Rule (Cal/OSHA Title 8 §5144): spraying two-component polyurethanes with isocyanates can cause asthma and sensitization. Use supplied-air respiratory protection, or whatever the SDS and a respiratory program require. Cal/OSHA Title 8 §5144 (respiratory protection) ↗
- Eye protection is needed when? Spraying, scraping overhead, sanding or using chemicals. Rule (Cal/OSHA Title 8 §3382): wear eye protection meeting ANSI Z87.1 when spraying, scraping or sanding overhead, using chemicals or strippers, or doing anything that produces flying debris or splashes. Cal/OSHA Title 8 §3382 (eye and face protection) ↗
- Workers using respirators must be? Medically evaluated, fit-tested and trained. Rule (Cal/OSHA Title 8 §5144): workers who use respirators must be medically evaluated, fit-tested (for tight-fitting types) and trained, under the employer's written respiratory protection program. Cal/OSHA Title 8 §5144 (respiratory protection) ↗
The Law & Business exam
Most California applicants also take the Law & Business exam. Its sections:
- Contracts21%
- Employment20%
- Business finances15%
- Safety14%
- Licensing13%
- Insurance & liens12%
- Public works5%
Contracts 21% of the exam · 257 practice questions
- A homeowner under 65 who signs a home improvement contract at home can cancel within? 3 business days. Rule (Civil Code §1689.6 and §7159): a buyer who signs a home improvement contract at home generally has 3 business days to cancel; the contract must include the Three-Day Right to Cancel notice. Seniors 65 and older get 5 business days. Civil Code §1689.6 (3-day right to cancel) ↗
- Statute of limitations to sue on a written contract in California? 4 years. Rule (Code of Civil Procedure §337): a lawsuit for breach of a written contract must be filed within 4 years after the breach. Oral contracts have a shorter 2-year limit (CCP §339). Code of Civil Procedure §337 (written contracts) ↗
Employment 20% of the exam · 241 practice questions
- An employee quits without notice. Final wages are due within? 72 hours. Rule (Labor Code §202): an employee who quits without giving at least 72 hours' notice must be paid within 72 hours. If the employee gave 72 hours' notice or more, final wages are due on the last day of work. Labor Code §202 (final pay within 72 hours) ↗
- Each paycheck must include? An itemized wage statement. Rule (Labor Code §226): with each paycheck, employers must give an itemized wage statement showing gross wages, total hours worked, all deductions, net wages, the pay period dates, the employee's name and last 4 digits of the SSN or an ID number, the employer's name and address, and all hourly rates with hours at each rate. Labor Code §226 (itemized wage statement) ↗
Business finances 15% of the exam · 147 practice questions
- Which statement shows the business's financial position at one point in time? Balance sheet. The balance sheet is a snapshot on one date. It lists what the business owns (assets), what it owes (liabilities) and the owners' equity, and it always balances: assets = liabilities + equity.
- The sales volume where revenue exactly covers all costs is the? Break-even point. The break-even point is the sales volume at which total revenue equals total costs (fixed plus variable), so profit is zero. Above break-even each sale adds profit; below it the business loses money.
Safety 14% of the exam · 158 practice questions
- Information on hazards of a chemical product is found on its? Safety Data Sheet (SDS). Rule (Title 8 §5194, Hazard Communication): manufacturers must provide a Safety Data Sheet (SDS) for every hazardous chemical, and employers must keep SDSs readily accessible to workers on each shift. Cal/OSHA Title 8 §5194 (Hazard Communication, safety data sheets) ↗
- When a ladder is used to reach an upper landing, its side rails must extend at least how far above the landing? 3 feet. Rule (29 CFR §1926.1053(b)(1); Cal/OSHA has the same rule): portable ladder side rails must extend at least 3 feet above the upper landing, or the ladder must be secured with a grab rail, so the worker has a handhold getting on and off. 29 CFR §1926.1053 (ladder 3 ft above landing) ↗
Licensing 13% of the exam · 152 practice questions
- An expired license can be renewed (without reapplying) for up to how long after it expires? 5 years. Rule (B&P §7141): an expired (delinquent) license can be renewed within 5 years after it expires by paying the renewal and delinquency fees. After 5 years it cannot be renewed and the business must apply for a new license, including any required exams. Bus. & Prof. Code §7141 (renewal within five years) ↗
- A lawsuit for a latent (hidden) construction defect must generally be filed within how many years of substantial completion? 10 years. Rule (Code of Civil Procedure §337.15): a lawsuit for a latent (hidden) construction defect must be filed within 10 years after substantial completion. Patent (obvious) defects fall under the shorter 4-year limit in CCP §337.1. Code of Civil Procedure §337.15 (10 years for latent defects) ↗
Insurance & liens 12% of the exam · 145 practice questions
- An owner must record a notice of completion within how many days after completion? 15. Rule (Civil Code §8182): an owner's notice of completion must be recorded within 15 days after completion of the work of improvement; a notice recorded later is not valid, and the longer 90-day lien periods then apply. Civil Code §8182 (notice of completion) ↗
- After receiving a progress payment, a prime contractor must pay its subcontractors within? 7 days. Rule (B&P §7108.5): a prime contractor must pay each subcontractor its share of a progress payment within 7 days after receiving it, unless the parties agreed otherwise in writing. Late payment carries a penalty of 2% per month on the amount due. Bus. & Prof. Code §7108.5 (prompt payment to subs) ↗
Public works 5% of the exam · 65 practice questions
- A public works payment bond is required when the contract exceeds? $25,000. Rule (Civil Code §9550): a direct contractor awarded a public works contract over $25,000 must give the public entity a payment bond before work starts, guaranteeing payment to subcontractors, laborers and suppliers. Civil Code §9550 (public works payment bond) ↗
- The annual DIR public works contractor registration fee is? $400. Rule (Labor Code §1725.5): contractors and subcontractors must register with the Department of Industrial Relations before bidding on or performing public works, and pay an annual registration fee — currently $400 — renewed every year (or up to three years at once). Labor Code §1725.5 (DIR registration) ↗
Questions people ask
What is on the California C-33 Painting and Decorating exam?
The exam is weighted by section: Surface Preparation & Repair 30%, Planning & Estimating 28%, Application of Paint & Finishes 21%, Safety 21%.
What is the format of the California C-33 Painting and Decorating exam?
Computer-based, multiple choice with four answer choices and one best answer. 3½ hours for each exam, trade and Law & Business (CSLB exam FAQ). CSLB does not publish the number of questions or the passing score. Closed book: no reference materials; a calculator is provided. Most applicants also take the Law & Business exam (included free with every trade exam here).
What should I study first for the California C-33 Painting and Decorating exam?
Start with the largest sections, which carry the most points: Surface Preparation & Repair (30%), Planning & Estimating (28%), Application of Paint & Finishes (21%). Then take a timed mock exam and spend extra time on whatever scored lowest.
Do I also need the Law & Business exam?
Most applicants for this license also take the Law & Business exam. It is included with this course, so you can practice both.
Where can I practice for the California C-33 Painting and Decorating exam?
LicenseExamReady has 1,347 practice questions for the California C-33 Painting and Decorating exam and the Law & Business exam, full mock exams weighted like the real test, explanations that cite the code section or rule, and a readiness score. New accounts get a free 3-day trial.
Are practice questions the same as the real exam?
No. Licensing boards keep their exams confidential. Good practice questions are written from the official exam outline and code books and teach the rule behind each answer.
Practice for the California C-33 Painting and Decorating exam
1,347 practice questions, full-length timed mock exams weighted like the real test, explanations with sources, and a readiness score that shows when you're ready to book the exam.
LicenseExamReady is an independent study tool, not affiliated with Contractors State License Board. How our questions are made.