All states / Arizona / B / Study guide
How to pass the Arizona B General Residential exam
A study guide for the Arizona B General Residential exam: what it covers, how much each section counts, the rules that come up most, and a study plan. Rules below link to their official source wherever one exists.
The exam at a glance
- 100 questions, 240 minutes, 70% to pass (PSI).
- Open book: 2018 International Residential Code and 29 CFR 1926 (OSHA).
- The same exam qualifies B, B-3 and CR-61.
Source: PSI content outline (B / B-3 / CR-61). Always confirm details with AZ ROC before test day.
What's on the exam
- Sitework17%
- Concrete17%
- Carpentry17%
- Thermal & Moisture Protection12%
- Masonry9%
- Finishes9%
- Doors & Windows7%
- Metal Framing6%
- Safety6%
Section weights from the official exam outline. Bigger sections are worth more points, so study them first.
A 4-step study plan
- Take a baseline test. Answer a full mock exam before studying so you know where you stand in each section.
- Study by weight, then by weakness. Start with Sitework (17%), Concrete (17%), Carpentry (17%), then move to whichever sections scored lowest on your baseline.
- Learn the rule, not just the answer. For every miss, read the explanation and the code section or statute it cites; on test day you'll need to know these references well.
- Repeat mock exams until you're consistently at 80% or more, which gives you a cushion above the passing score. Retake the questions you missed until they stick.
Key rules to know, by section
A few of the facts that come up in each section, with the answer and the source. The full course has 500 questions with explanations.
Sitework 17% of the exam · 19 practice questions
- Batter boards are used to? Hold string lines marking the building outside the excavation. Batter boards are horizontal boards set on stakes a few feet outside the building corners. String lines stretched between them mark the exact building lines and can be removed and replaced.
- Footing excavations should be inspected? Before concrete is placed. Rule (2018 IRC §R109.1.1): the foundation inspection is made after trenches are excavated and forms are erected, and when all materials for the foundation are delivered on the job, but before any concrete is placed. 2018 IRC §R109.1.1 (Foundation inspection) ↗
- A sheepsfoot roller is best for compacting? Clay (cohesive) soils. A sheepsfoot roller has a drum covered with protruding feet that knead and press into cohesive (clay) soils, breaking up clods and forcing out air from the bottom of the lift upward.
Concrete 17% of the exam · 26 practice questions
- Footings must be placed at least how far below undisturbed ground (2018 IRC)? 12 in. Rule (2018 IRC §R403.1.4): exterior footings must be placed at least 12 in below the undisturbed ground surface. Where frost applies, the footing must also go below the frost depth set in Table R301.2(1) (R403.1.4.1). 2018 IRC §R403.1.4 (Minimum depth) ↗
- Control joints in a slab are cut to a depth of about? 1/4 of thickness. Control (contraction) joints are cut or tooled to about one-quarter of the slab thickness (for example, 1 in deep in a 4 in slab). This creates a weakened plane so that shrinkage cracks form in a straight line at the joint instead of randomly across the slab.
- Slabs on ground are placed over a base course of clean graded sand, gravel or crushed stone at least? 4 in thick. Rule (2018 IRC §R506.2.2): a base course at least 4 in thick of clean graded sand, gravel or crushed stone (passing a 2 in sieve) is placed on the prepared subgrade under a slab on ground. It provides uniform support and breaks capillary rise of moisture. 2018 IRC §R506.2.2 (Base) ↗
Carpentry 17% of the exam · 37 practice questions
- Required guards on open-sided walking surfaces in a dwelling must be at least (2018 IRC)? 36 in. Rule (2018 IRC §R312.1.2): required guards at open-sided walking surfaces, including stairs, ramps and landings, must be at least 36 in high, measured vertically above the adjacent walking surface. 2018 IRC §R312.1.2 (Guard height) ↗
- End joints in a double top plate must be offset at least? 24 in. Rule (2018 IRC §R602.3.2): wood stud walls must be capped with a double top plate, installed to provide overlapping at corners and intersections with bearing partitions. End joints in the top plates must be offset at least 24 in. 2018 IRC §R602.3.2 (Top plate) ↗
- What is the actual size of a 2×4? 1-1/2 × 3-1/2 in. Nominal lumber sizes are the rough-sawn size before drying and planing (surfacing). A nominal 2×4 is actually 1-1/2 × 3-1/2 in. The rule of thumb: nominal 2, 4 and 6 in dimensions lose 1/2 in; nominal 8 in and wider lose 3/4 in.
Thermal & Moisture Protection 12% of the exam · 21 practice questions
- Drip edge pieces must overlap at least? 2 in. Rule (2018 IRC §R905.2.8.5): adjacent pieces of drip edge must overlap at least 2 in. 2018 IRC §R905.2.8.5 (Drip edge) ↗
- A higher R-value insulation means? More resistance to heat flow. R-value measures thermal resistance, how well a material resists conductive heat flow. A higher R-value means more resistance and better insulation. R-values of layers in series add together (R-13 cavity insulation plus R-5 continuous insulation = R-18).
- A cricket is required on the high side of a chimney wider than? 30 in. Rule (2018 IRC §R1003.20): a chimney cricket (saddle) must be provided where the chimney is more than 30 in wide, measured parallel to the ridge line, and is not intersected by the ridge line. 2018 IRC §R1003.20 (Chimney crickets) ↗
Masonry 9% of the exam · 16 practice questions
- Type N mortar is typically used for? General above-grade exterior and interior walls. Type N mortar is a medium-strength, general-purpose mortar for above-grade exterior and interior walls (including veneer) that are not heavily loaded.
- Weep holes in masonry veneer are spaced no more than? 33 in o.c. Rule (2018 IRC §R703.8.6): weepholes must be provided in the outside wythe of masonry veneer at a maximum spacing of 33 in on center, with a minimum diameter of 3/16 in, located immediately above the flashing. 2018 IRC §R703.8.6 (Weepholes) ↗
- Efflorescence on masonry is caused by? Water carrying soluble salts to the surface. Efflorescence is the white, powdery deposit on masonry surfaces. Water dissolves soluble salts in the masonry, mortar or soil, carries them to the surface, and evaporates, leaving the salts behind.
Finishes 9% of the exam · 17 practice questions
- Shower and tub walls need a nonabsorbent surface to a height of at least how far above the floor? 72 in. Rule (2018 IRC §R307.2): bathtub and shower floors, walls above bathtubs with installed showerheads, and walls in shower compartments must be finished with a nonabsorbent surface. 2018 IRC §R307.2 (Bathtub and shower spaces) ↗
- Typical maximum screw spacing for gypsum board on ceilings (2018 IRC Table R702.3.5) is? 12 in. Rule (2018 IRC Table R702.3.5): for gypsum board applied to ceilings with screws, the maximum fastener spacing is 12 in on center (with framing at 16 or 24 in o.c.). On walls, screws may be spaced up to 16 in on center. 2018 IRC Table R702.3.5 (gypsum board application) ↗
- Corner bead on outside drywall corners? Protects and straightens the corner. Corner bead, made of metal, vinyl or paper-faced metal, is installed on outside drywall corners. It protects the vulnerable corner from impact damage and creates a straight, true edge for the joint compound to be feathered against.
Doors & Windows 7% of the exam · 16 practice questions
- A window well for a below-grade escape window needs a ladder or steps when it is deeper than? 44 in. Rule (2018 IRC §R310.2.3.1): window wells with a vertical depth greater than 44 in must be equipped with a permanently affixed ladder or steps usable with the window in the fully open position. 2018 IRC §R310.2.3.1 (Ladder and steps) ↗
- Every dwelling needs at least one egress door that is side-hinged with a clear width of at least? 32 in. Rule (2018 IRC §R311.2): every dwelling unit must have at least one egress door that is side-hinged with a clear width of at least 32 in, measured between the face of the door and the stop with the door open 90 degrees, and a clear height of at least 78 in, measured from the top of the threshold to the bottom of the stop. 2018 IRC §R311.2 (Egress door) ↗
- A door between an attached garage and the house must be? Solid wood or solid/honeycomb-core steel at least 1-3/8 in thick, or 20-minute fire-rated. Rule (2018 IRC §R302.5.1): openings from a private garage directly into a room used for sleeping are not permitted. 2018 IRC §R302.5.1 (Garage opening protection) ↗
Metal Framing 6% of the exam · 8 practice questions
- When steel framing contacts dissimilar metals like copper, you should? Isolate them to prevent galvanic corrosion. When two different metals touch in the presence of moisture (an electrolyte), the less noble metal corrodes. Galvanized steel framing in contact with copper pipe will corrode quickly.
- Cold-formed steel studs used in IRC wall framing must have a minimum protective coating of? G60 galvanizing (or equivalent). Rule (2018 IRC §R603.2.2, corrosion protection): load-bearing cold-formed steel framing members must have a metallic coating at least G60 galvanizing (or an equivalent coating such as AZ50 aluminum-zinc). 2018 IRC §R603.2.2 (Corrosion protection) ↗
- The U-shaped member that receives the ends of steel studs is the? Track. In cold-formed steel framing, studs and joists are C-shaped (with lips), while the track is a U-shaped channel without lips.
Safety 6% of the exam · 18 practice questions
- Protective systems for trenches deeper than how much must be designed by a registered professional engineer? 20 ft. Rule (OSHA 29 CFR 1926.652(b) and (c)): sloping and benching systems, and support or shield systems, for excavations greater than 20 ft deep must be designed by a registered professional engineer. OSHA 29 CFR 1926.652 (Requirements for protective systems) ↗
- Employers must keep Safety Data Sheets for hazardous chemicals? Readily accessible to workers. Rule (OSHA Hazard Communication, 29 CFR 1926.59, which adopts 1910.1200): employers must keep copies of the Safety Data Sheets for each hazardous chemical used, and ensure they are readily accessible to employees during each work shift when they are in their work areas.
- Scaffolds and components must support their own weight and at least how many times the intended load? 4. Rule (OSHA 29 CFR 1926.451(a)(1)): each scaffold and scaffold component must be capable of supporting, without failure, its own weight and at least 4 times the maximum intended load applied or transmitted to it. OSHA 29 CFR 1926.451 (Scaffolds — general requirements) ↗
The Statutes & Rules exam
Most Arizona applicants also take the Statutes & Rules exam. Its sections:
- Licensing & Classifications20%
- Contracts, Advertising & Payment20%
- Qualifying Party & License Upkeep15%
- Bonds & Recovery Fund15%
- Mechanics' Liens15%
- Complaints & Penalties15%
Licensing & Classifications 20% of the exam · 137 practice questions
- An owner may build or improve their own property without a license if the structure is? Intended solely for the owner's occupancy, not for sale or rent. Rule (A.R.S. § 32-1121(A)(5)): owners may build or improve structures on their own property without a license only if the work is intended solely for their own occupancy and not offered for sale or rent. A.R.S. §32-1121 (Persons not required to be licensed) ↗
- The B-3 General Remodeling and Repair license covers? Remodeling and repair of existing residential structures. Rule (A.A.C. R4-9-103, B-3 General Remodeling and Repair): the B-3 license covers remodeling and repair of existing residential structures, including the R-7 carpentry scope. Other trades such as electrical and plumbing must be subcontracted. A.A.C. R4-9-103 (B-3 General Remodeling and Repair), ROC rules p. 11 ↗
Contracts, Advertising & Payment 20% of the exam · 36 practice questions
- Under the Arizona Prompt Pay Act, an owner has how long to approve or object to a progress billing? 14 days. Rule (Arizona Prompt Pay Act, A.R.S. § 32-1182): an owner has 14 days after receiving a progress billing to certify and approve it, or to object in writing. A.R.S. §32-1182 (Progress payments by owner) ↗
- An unlicensed person advertises 'Kitchen remodels — call us!' without the required statement. This violates? Arizona's advertising rules and the consumer fraud act (A.R.S. § 44-1522). Rule (A.R.S. § 32-1121(C) and § 44-1522): an unlicensed person who advertises for work that requires a license, or omits the required 'not a licensed contractor' statement, violates Arizona's advertising rules and commits consumer fraud. A.R.S. §32-1121 (Persons not required to be licensed) ↗
Qualifying Party & License Upkeep 15% of the exam · 51 practice questions
- If the licensee does not replace its qualifying party in time, the license is? Automatically suspended by operation of law. Rule (A.R.S. § 32-1127.01(C)): if the licensee doesn't replace its qualifying party within the 60-day period, the license is automatically suspended by operation of law until a qualified replacement is approved. A.R.S. §32-1127.01 (Qualifying party disassociation) ↗
- Reactivating an inactive license requires? The renewal fee and 30 days' written notice. Rule (A.R.S. § 32-1125.01): to reactivate an inactive license, the licensee gives the registrar 30 days' written notice and pays the renewal fee. No new exam is required. A.R.S. §32-1125.01 (Inactive license) ↗
Bonds & Recovery Fund 15% of the exam · 38 practice questions
- Residential and dual licensees must either join the Residential Contractors' Recovery Fund or post an additional bond of? $200,000. Rule (A.R.S. § 32-1152): residential and dual licensees must either participate in the Residential Contractors' Recovery Fund or post an additional bond of $200,000. A.R.S. §32-1152 (Bonds) ↗
- Recovery Fund actual damages are the reasonable cost to complete the contract and repair defective work? Minus the unpaid contract price. Rule (A.R.S. § 32-1132.01(H)): Recovery Fund actual damages are the reasonable cost to complete the contract and repair defective work, minus any unpaid contract price the owner still owes. A.R.S. §32-1132.01 (Recovery fund damages and limits) ↗
Mechanics' Liens 15% of the exam · 29 practice questions
- If the owner records and serves a notice of completion, a lien must be recorded within? 60 days after the notice. Rule (A.R.S. § 33-993(A)): if the owner records and serves a notice of completion, a lien must be recorded within 60 days after the notice is recorded. A.R.S. §33-993 (Perfecting a lien) ↗
- A preliminary notice includes an estimate of? The total price of labor and materials to be furnished. Rule (A.R.S. § 33-992.01): a preliminary notice must include an estimate of the total price of the labor, materials and equipment the claimant will furnish. A.R.S. §33-992.01 (Preliminary twenty-day notice) ↗
Complaints & Penalties 15% of the exam · 31 practice questions
- The maximum civil penalty for multiple violations committed on the same day is? $2,500. Rule (A.R.S. § 32-1166.01): the Registrar may issue citations with civil penalties to persons who contract without a license. The total civil penalty for all violations committed on the same day may not exceed $2,500. A.R.S. §32-1166.01 (Citations; civil penalties) ↗
- A homeowner who hires an unlicensed contractor generally? Cannot claim from the Recovery Fund. Rule (A.R.S. § 32-1132): the Recovery Fund covers only damage caused by appropriately licensed residential contractors, so a homeowner who hires an unlicensed contractor generally can't claim from it. A.R.S. §32-1132 (Residential contractors' recovery fund) ↗
Questions people ask
What is on the Arizona B General Residential exam?
The exam is weighted by section: Sitework 17%, Concrete 17%, Carpentry 17%, Thermal & Moisture Protection 12%, Masonry 9%, Finishes 9%, Doors & Windows 7%, Metal Framing 6%, Safety 6%.
What is the format of the Arizona B General Residential exam?
100 questions, 240 minutes, 70% to pass (PSI). Open book: 2018 International Residential Code and 29 CFR 1926 (OSHA). The same exam qualifies B, B-3 and CR-61.
What should I study first for the Arizona B General Residential exam?
Start with the largest sections, which carry the most points: Sitework (17%), Concrete (17%), Carpentry (17%). Then take a timed mock exam and spend extra time on whatever scored lowest.
Do I also need the Statutes & Rules exam?
Most applicants for this license also take the Statutes & Rules exam. It is included with this course, so you can practice both.
Where can I practice for the Arizona B General Residential exam?
LicenseExamReady has 500 practice questions for the Arizona B General Residential exam and the Statutes & Rules exam, full mock exams weighted like the real test, explanations that cite the code section or rule, and a readiness score. New accounts get a free 3-day trial.
Are practice questions the same as the real exam?
No. Licensing boards keep their exams confidential. Good practice questions are written from the official exam outline and code books and teach the rule behind each answer.
Practice for the Arizona B General Residential exam
500 practice questions, full-length timed mock exams weighted like the real test, explanations with sources, and a readiness score that shows when you're ready to book the exam.
LicenseExamReady is an independent study tool, not affiliated with Arizona Registrar of Contractors. How our questions are made.