All states / Arizona / R-37R / Study guide

How to pass the Arizona R-37R Plumbing exam

A study guide for the Arizona R-37R Plumbing exam: what it covers, how much each section counts, the rules that come up most, and a study plan. Rules below link to their official source wherever one exists.

The exam at a glance

  • 100 questions, 240 minutes, 70% to pass (PSI).
  • Open book: 2018 IPC, IFGC and IMC, NFPA 13/13D/13R, A.A.C. Title 18 Ch. 9 and 29 CFR 1926.

Source: PSI content outline (R-37R). Always confirm details with AZ ROC before test day.

What's on the exam

  • Drainage, Waste & Vents16%
  • Water Supply Systems13%
  • General Knowledge & Regulations10%
  • Fuel Gas10%
  • Septic & Sewer10%
  • Plumbing Fixtures & Water Heaters7%
  • Backflow Prevention5%
  • Roof Drains & Storm Drainage5%
  • Specialty Plumbing, Interceptors & Traps5%
  • Isometric Analysis5%
  • Fire Sprinklers5%
  • Excavation5%
  • Indirect Waste4%

Section weights from the official exam outline. Bigger sections are worth more points, so study them first.

A 4-step study plan

  1. Take a baseline test. Answer a full mock exam before studying so you know where you stand in each section.
  2. Study by weight, then by weakness. Start with Drainage, Waste & Vents (16%), Water Supply Systems (13%), General Knowledge & Regulations (10%), then move to whichever sections scored lowest on your baseline.
  3. Learn the rule, not just the answer. For every miss, read the explanation and the code section or statute it cites; on test day you'll need to know these references well.
  4. Repeat mock exams until you're consistently at 80% or more, which gives you a cushion above the passing score. Retake the questions you missed until they stick.

Key rules to know, by section

A few of the facts that come up in each section, with the answer and the source. The full course has 520 questions with explanations.

Drainage, Waste & Vents 16% of the exam · 27 practice questions

  • An open vent terminal may not be within 10 ft horizontally of an openable window or door unless it is at least how far above the top of the opening? 3 ft. Rule (2018 IPC §903.5): an open vent terminal from a drainage system may not be located directly beneath any door, openable window or other air intake opening of the building or an adjacent building, nor within 10 ft horizontally of such an opening unless it is at least 3 ft above the top of the opening. 2018 IPC §903.5 (Location of vent terminal) ↗
  • A vertical vent pipe installed to provide circulation of air to and from the drainage system, running alongside the stack, is a? Vent stack. Rule (IPC Chapter 2, definitions): a vent stack is a vertical vent pipe installed primarily for the purpose of providing circulation of air to and from the drainage system, and which extends through one or more stories.
  • Cleanouts on horizontal drains are required at intervals of not more than? 100 ft. Rule (2018 IPC §708.1.1): horizontal drainage pipes in buildings must have cleanouts located at intervals of not more than 100 ft. Building sewers likewise need cleanouts at intervals of not more than 100 ft (§708.1.2). 2018 IPC §708.1.1 (Horizontal drains and building drains) ↗

Water Supply Systems 13% of the exam · 22 practice questions

  • Maximum flow rate for a showerhead under IPC Table 604.4 is? 2.5 gpm at 80 psi. Rule (2018 IPC §604.4, Table 604.4): the maximum flow rate for a showerhead is 2.5 gpm at 80 psi. 2018 IPC Table 604.4 (maximum flow rates) ↗
  • PVC pipe may be used for? Cold water service outside the building (not hot water). Rule (2018 IPC §605.3–§605.4, Tables 605.3 and 605.4): PVC pipe is listed for cold water service pipe outside the building (Table 605.3) but is not listed for water distribution pipe inside the building (Table 605.4), and it may never be used for hot water. 2018 IPC Table 605.3 (water service pipe) ↗
  • Maximum flow for a private lavatory faucet under IPC Table 604.4? 2.2 gpm at 60 psi. Rule (2018 IPC §604.4, Table 604.4): a private lavatory faucet is limited to 2.2 gpm at 60 psi. Public lavatory faucets are limited to 0.5 gpm (metering faucets to 0.25 gal per cycle), because public restrooms use short hand-washing cycles. 2018 IPC Table 604.4 (maximum flow rates) ↗

General Knowledge & Regulations 10% of the exam · 19 practice questions

  • Arizona's residential plumbing license is issued by? The Arizona Registrar of Contractors. Rule (A.R.S. Title 32, Chapter 10): in Arizona, contractor licenses, including residential plumbing (R-37R, and the dual-classification plumbing license), are issued by the Arizona Registrar of Contractors (ROC).
  • Copper tube joints that are soldered require? Cleaned surfaces, flux and lead-free solder. Rule (2018 IPC §605.12.3): soldered copper joints must be made per ASTM B828: cut the tube square, ream it, clean the tube end and fitting socket to bright metal, apply flux (ASTM B813), assemble, and heat until the lead-free solder flows into the joint by capillary action. 2018 IPC §605.12.3 (Solder joints, lead-free solder) ↗
  • Accessible plumbing fixtures follow? ICC A117.1 as referenced by the building code. Rule (2018 IPC §404 and IBC Chapter 11): accessible plumbing fixtures and facilities must be designed and installed per ICC A117.1, as referenced by the building code.

Fuel Gas 10% of the exam · 22 practice questions

  • Underground plastic (PE) gas piping must have a tracer wire of at least? 18 AWG. Rule (2018 IFGC §404.17.3): an electrically continuous, corrosion-resistant tracer wire (not less than 18 AWG) or tracer tape must be buried with underground plastic (PE) gas piping to make it locatable. 2018 IFGC §404.17.3 (Tracer) ↗
  • Most IFGC gas pipe sizing tables for low-pressure natural gas assume a pressure drop of? 0.5 in w.c. Rule (2018 IFGC §402.4, Table 402.4(2)): the commonly used IFGC tables for low-pressure natural gas (inlet pressure less than 2 psi, specific gravity 0.60) are based on an allowable pressure drop of 0.5 in w.c. (Table 402.4(1) uses 0.3 in w.c.). 2018 IFGC Table 402.4(2) (pipe sizing, 0.5 in. w.c. pressure drop) ↗
  • Underground gas piping must be buried at least? 12 in (8 in for individual outdoor appliance lines). Rule (2018 IFGC §404.12): underground gas piping must be installed with at least 12 in of cover below grade. 2018 IFGC §404.12 (Minimum burial depth) ↗

Septic & Sewer 10% of the exam · 18 practice questions

  • Building sewers must have cleanouts at intervals of not more than? 100 ft. Rule (2018 IPC §708.1.2): building sewers must have cleanouts located at intervals of not more than 100 ft. Manholes may be required on larger sewers. Cleanouts let the sewer be rodded or jetted when it clogs. 2018 IPC §708.1.2 (Building sewers) ↗
  • A backwater valve is installed to? Prevent sewage from backing up into fixtures below the upstream manhole level. Rule (2018 IPC §715): where the flood level rims of fixtures are located below the elevation of the next upstream manhole cover of the public sewer, the fixtures must be protected by a backwater valve, so sewage cannot back up into the building when the public sewer surcharges.
  • The scum layer in a septic tank consists of? Grease and light solids floating on top. In a septic tank, the scum layer is the floating layer of grease, oils, fats and light solids on top of the liquid. Heavy solids settle to the bottom as sludge. The clearer liquid between them (effluent) flows out to the disposal field. ADEQ On-site Wastewater (A.A.C. Title 18, Ch. 9) ↗

Plumbing Fixtures & Water Heaters 7% of the exam · 19 practice questions

  • A water heater T&P relief discharge pipe must terminate? Not more than 6 in above the floor or waste receptor flood rim. Rule (2018 IPC §504.6): the discharge piping from a water heater relief valve must not be directly connected to the drainage system; it must discharge through an air gap to the floor, a waste receptor or the outdoors, and must terminate not more than 6 in above the floor or the flood level rim of the waste receptor. 2018 IPC §504.6 (Relief valve discharge piping) ↗
  • Bathtub fillers must have a device limiting water temperature to? 120°F. Rule (2018 IPC §412.5): the hot water supplied to bathtubs and whirlpool bathtubs must be limited to a maximum temperature of 120°F by a water-temperature limiting device conforming to ASSE 1070, ASME A112.1070 or CSA B125.70, except where the bathtub filler is protected by a shower valve that meets §412.3. 2018 IPC §412.5 (Bathtub and whirlpool bathtub valves) ↗
  • Fuel-burning water heaters in garages must have ignition sources at least how high above the floor? 18 in. Rule (2018 IPC §502.1.1 and IFGC §305.3): fuel-fired water heaters with an ignition source installed in residential garages (and hazardous locations) must be elevated so that the source of ignition is not less than 18 in above the floor. 2018 IPC §502.1.1 (Water heater elevation and protection) ↗

Backflow Prevention 5% of the exam · 13 practice questions

  • Hose bibbs must be protected against backflow by? A listed vacuum breaker (hose connection backflow preventer). Rule (2018 IPC §608.16.4.2): sillcocks, hose bibbs, wall hydrants and other openings with a hose connection must be protected by an atmospheric-type or pressure-type vacuum breaker or a permanently attached hose connection vacuum breaker. 2018 IPC §608.16.4.2 (Hose connections) ↗
  • A reduced pressure principle (RP) assembly protects against? High hazards, both backpressure and backsiphonage. Rule (2018 IPC §608.1, Table 608.1): a reduced pressure principle (RP) backflow prevention assembly protects against both backpressure and backsiphonage and is approved for high hazard (contaminant) as well as low hazard (pollutant) applications. 2018 IPC Table 608.1 (application of backflow preventers) ↗
  • A pressure vacuum breaker must be installed at least how far above the highest downstream outlet? 12 in. Rule (2018 IPC §608.14.5, pressure vacuum breaker assemblies): a PVB must be installed with its critical level not less than 12 in above the highest elevation of downstream piping and the flood level rim of the receptor it serves. 2018 IPC §608.14.5 (Pressure vacuum breaker assemblies) ↗

Roof Drains & Storm Drainage 5% of the exam · 8 practice questions

  • Roof drains should have strainers that? Extend above the roof surface (at least 4 in). Rule (IPC §1105.2): roof drains must have strainers that extend not less than 4 in above the surface of the roof immediately adjacent to the drain, with an available inlet area above roof level of not less than 1.5 times the area of the conductor or leader.
  • Roof drain strainers must extend at least how far above the roof surface? 4 in. Rule (IPC §1105.2, roof drain strainers): roof drain strainers must extend not less than 4 in above the surface of the roof immediately adjacent to the roof drain, and must have an available inlet area above roof level of not less than 1.5 times the area of the conductor or leader to which the drain is connected.
  • Storm drainage piping is sized based on? Roof area and the local rainfall rate. Rule (IPC Chapter 11, §1106): storm drainage piping (leaders, horizontal storm drains and building storm sewers) is sized based on the roof (or other surface) area drained and the local rainfall rate, using the 100-year hourly rainfall rate from Figure 1106.1 or local data, with the sizing tables in §1106.

Specialty Plumbing, Interceptors & Traps 5% of the exam · 12 practice questions

  • Floor drains that rarely receive water need? A trap seal primer or approved seal protection. Rule (2018 IPC §1002.4.1): where a trap seal is subject to loss by evaporation, as with floor drains that rarely receive water, it must be protected by a trap seal primer valve (ASSE 1018 or 1044), a barrier-type floor drain trap seal protection device (ASSE 1072), a deep-seal trap, or another approved means. 2018 IPC §1002.4.1 (Trap seal protection) ↗
  • Grease interceptors are required for? Food service establishments discharging fats, oils and grease. Rule (2018 IPC §1003.3): grease interceptors (or automatic grease removal devices) are required to receive the drainage from fixtures and equipment with grease-laden waste in food processing establishments, restaurants, cafeterias, clubs and similar food service establishments. 2018 IPC §1003.3 (Grease interceptors) ↗
  • The vertical distance from a fixture outlet to the trap weir may not exceed? 24 in. Rule (2018 IPC §1002.1): the vertical distance from the fixture outlet to the trap weir may not exceed 24 in, and the horizontal distance from the center line of the fixture outlet to the centerline of the trap inlet may not exceed 30 in. 2018 IPC §1002.1 (Fixture traps) ↗

Isometric Analysis 5% of the exam · 6 practice questions

  • An isometric piping drawing shows horizontal lines drawn at? 30° from horizontal. An isometric piping drawing shows a three-dimensional piping system on a flat sheet. Horizontal pipes are drawn at 30 degrees from the horizontal (to the right or left, depending on direction), and vertical pipes are drawn as vertical lines.
  • In an isometric DWV drawing, you count fixture units by? Adding the DFU of all fixtures draining into each section. To find the DFU load on each section of an isometric DWV drawing, add the drainage fixture unit values (IPC Table 709.1) of all fixtures that drain into that section, working downstream from the most remote fixture toward the building drain.
  • On an isometric drawing, a vertical stack is drawn as a? Vertical line. On an isometric drawing, vertical pipes such as soil and vent stacks are drawn as true vertical lines, while horizontal pipes are drawn at 30-degree angles.

Fire Sprinklers 5% of the exam · 11 practice questions

  • Multipurpose residential sprinkler systems? Combine domestic water and sprinkler piping (permitted under NFPA 13D). Rule (NFPA 13D): a multipurpose residential sprinkler system uses the same piping to supply both the domestic water fixtures and the fire sprinklers.

Excavation 5% of the exam · 13 practice questions

  • Protective systems for excavations over 20 ft deep must be designed by a? Registered professional engineer. Rule (OSHA 29 CFR 1926.652(b) and (c)): sloping and benching systems for excavations greater than 20 ft deep, and support or shield systems beyond the limits of the Appendix tables and tabulated data, must be designed by a registered professional engineer. OSHA 29 CFR 1926.652 (Requirements for protective systems) ↗
  • Spoil piles must be kept at least how far from the edge of a trench? 2 ft. Rule (OSHA 29 CFR 1926.651(j)(2)): employees must be protected from excavated or other materials or equipment that could fall or roll into excavations. OSHA 29 CFR 1926.651(j)(2) (Specific excavation requirements) ↗
  • Trenches 5 ft or deeper need? A protective system (sloping, shoring or shielding). Rule (OSHA 29 CFR 1926.652(a)(1)): each employee in an excavation must be protected from cave-ins by an adequate protective system: sloping, benching, shoring or shielding (trench box). OSHA 29 CFR 1926.652 (Requirements for protective systems) ↗

Indirect Waste 4% of the exam · 8 practice questions

  • Condensate from air conditioning equipment must discharge? To an approved place of disposal. Rule (IMC §307.2): condensate from all cooling coils and evaporators, and from fuel-burning condensing appliances, must be conveyed from the drain pan outlet to an approved place of disposal.
  • An air gap for indirect waste must be at least twice the diameter of the indirect waste pipe and not less than? 1 in. Rule (2018 IPC §802.3.1): the air gap between the indirect waste pipe and the flood level rim of the waste receptor must be not less than twice the effective opening of the indirect waste pipe, and not less than 1 in. 2018 IPC §802.3.1 (Air gap) ↗
  • Water softener and water treatment discharge must connect to the drainage system? Through an indirect waste (air gap or air break). Rule (2018 IPC §802.1): certain equipment must discharge to the drainage system through an indirect waste pipe (an air gap or air break) instead of a direct connection. 2018 IPC §802.1 (Indirect waste, where required) ↗

The Statutes & Rules exam

Most Arizona applicants also take the Statutes & Rules exam. Its sections:

  • Licensing & Classifications20%
  • Contracts, Advertising & Payment20%
  • Qualifying Party & License Upkeep15%
  • Bonds & Recovery Fund15%
  • Mechanics' Liens15%
  • Complaints & Penalties15%

Licensing & Classifications 20% of the exam · 137 practice questions

  • An owner may build or improve their own property without a license if the structure is? Intended solely for the owner's occupancy, not for sale or rent. Rule (A.R.S. § 32-1121(A)(5)): owners may build or improve structures on their own property without a license only if the work is intended solely for their own occupancy and not offered for sale or rent. A.R.S. §32-1121 (Persons not required to be licensed) ↗
  • The B-3 General Remodeling and Repair license covers? Remodeling and repair of existing residential structures. Rule (A.A.C. R4-9-103, B-3 General Remodeling and Repair): the B-3 license covers remodeling and repair of existing residential structures, including the R-7 carpentry scope. Other trades such as electrical and plumbing must be subcontracted. A.A.C. R4-9-103 (B-3 General Remodeling and Repair), ROC rules p. 11 ↗

Contracts, Advertising & Payment 20% of the exam · 36 practice questions

  • Under the Arizona Prompt Pay Act, an owner has how long to approve or object to a progress billing? 14 days. Rule (Arizona Prompt Pay Act, A.R.S. § 32-1182): an owner has 14 days after receiving a progress billing to certify and approve it, or to object in writing. A.R.S. §32-1182 (Progress payments by owner) ↗
  • An unlicensed person advertises 'Kitchen remodels — call us!' without the required statement. This violates? Arizona's advertising rules and the consumer fraud act (A.R.S. § 44-1522). Rule (A.R.S. § 32-1121(C) and § 44-1522): an unlicensed person who advertises for work that requires a license, or omits the required 'not a licensed contractor' statement, violates Arizona's advertising rules and commits consumer fraud. A.R.S. §32-1121 (Persons not required to be licensed) ↗

Qualifying Party & License Upkeep 15% of the exam · 51 practice questions

  • If the licensee does not replace its qualifying party in time, the license is? Automatically suspended by operation of law. Rule (A.R.S. § 32-1127.01(C)): if the licensee doesn't replace its qualifying party within the 60-day period, the license is automatically suspended by operation of law until a qualified replacement is approved. A.R.S. §32-1127.01 (Qualifying party disassociation) ↗
  • Reactivating an inactive license requires? The renewal fee and 30 days' written notice. Rule (A.R.S. § 32-1125.01): to reactivate an inactive license, the licensee gives the registrar 30 days' written notice and pays the renewal fee. No new exam is required. A.R.S. §32-1125.01 (Inactive license) ↗

Bonds & Recovery Fund 15% of the exam · 38 practice questions

  • Residential and dual licensees must either join the Residential Contractors' Recovery Fund or post an additional bond of? $200,000. Rule (A.R.S. § 32-1152): residential and dual licensees must either participate in the Residential Contractors' Recovery Fund or post an additional bond of $200,000. A.R.S. §32-1152 (Bonds) ↗
  • Recovery Fund actual damages are the reasonable cost to complete the contract and repair defective work? Minus the unpaid contract price. Rule (A.R.S. § 32-1132.01(H)): Recovery Fund actual damages are the reasonable cost to complete the contract and repair defective work, minus any unpaid contract price the owner still owes. A.R.S. §32-1132.01 (Recovery fund damages and limits) ↗

Mechanics' Liens 15% of the exam · 29 practice questions

  • If the owner records and serves a notice of completion, a lien must be recorded within? 60 days after the notice. Rule (A.R.S. § 33-993(A)): if the owner records and serves a notice of completion, a lien must be recorded within 60 days after the notice is recorded. A.R.S. §33-993 (Perfecting a lien) ↗
  • A preliminary notice includes an estimate of? The total price of labor and materials to be furnished. Rule (A.R.S. § 33-992.01): a preliminary notice must include an estimate of the total price of the labor, materials and equipment the claimant will furnish. A.R.S. §33-992.01 (Preliminary twenty-day notice) ↗

Complaints & Penalties 15% of the exam · 31 practice questions

  • The maximum civil penalty for multiple violations committed on the same day is? $2,500. Rule (A.R.S. § 32-1166.01): the Registrar may issue citations with civil penalties to persons who contract without a license. The total civil penalty for all violations committed on the same day may not exceed $2,500. A.R.S. §32-1166.01 (Citations; civil penalties) ↗
  • A homeowner who hires an unlicensed contractor generally? Cannot claim from the Recovery Fund. Rule (A.R.S. § 32-1132): the Recovery Fund covers only damage caused by appropriately licensed residential contractors, so a homeowner who hires an unlicensed contractor generally can't claim from it. A.R.S. §32-1132 (Residential contractors' recovery fund) ↗

Questions people ask

What is on the Arizona R-37R Plumbing exam?

The exam is weighted by section: Drainage, Waste & Vents 16%, Water Supply Systems 13%, General Knowledge & Regulations 10%, Fuel Gas 10%, Septic & Sewer 10%, Plumbing Fixtures & Water Heaters 7%, Backflow Prevention 5%, Roof Drains & Storm Drainage 5%, Specialty Plumbing, Interceptors & Traps 5%, Isometric Analysis 5%, Fire Sprinklers 5%, Excavation 5%, Indirect Waste 4%.

What is the format of the Arizona R-37R Plumbing exam?

100 questions, 240 minutes, 70% to pass (PSI). Open book: 2018 IPC, IFGC and IMC, NFPA 13/13D/13R, A.A.C. Title 18 Ch. 9 and 29 CFR 1926.

What should I study first for the Arizona R-37R Plumbing exam?

Start with the largest sections, which carry the most points: Drainage, Waste & Vents (16%), Water Supply Systems (13%), General Knowledge & Regulations (10%). Then take a timed mock exam and spend extra time on whatever scored lowest.

Do I also need the Statutes & Rules exam?

Most applicants for this license also take the Statutes & Rules exam. It is included with this course, so you can practice both.

Where can I practice for the Arizona R-37R Plumbing exam?

LicenseExamReady has 520 practice questions for the Arizona R-37R Plumbing exam and the Statutes & Rules exam, full mock exams weighted like the real test, explanations that cite the code section or rule, and a readiness score. New accounts get a free 3-day trial.

Are practice questions the same as the real exam?

No. Licensing boards keep their exams confidential. Good practice questions are written from the official exam outline and code books and teach the rule behind each answer.

Practice for the Arizona R-37R Plumbing exam

520 practice questions, full-length timed mock exams weighted like the real test, explanations with sources, and a readiness score that shows when you're ready to book the exam.

LicenseExamReady is an independent study tool, not affiliated with Arizona Registrar of Contractors. How our questions are made.