The exam at a glance

  • Computer-based, multiple choice with four answer choices and one best answer.
  • 3½ hours for each exam, trade and Law & Business (CSLB exam FAQ). CSLB does not publish the number of questions or the passing score.
  • Closed book: no reference materials; a calculator is provided.
  • Most applicants also take the Law & Business exam (included free with every trade exam here).

Source: CSLB C-39 study guide. Always confirm details with CSLB before test day.

What's on the exam

  • Steep-Slope Roofing26%
  • Planning & Estimating22%
  • Safety22%
  • Low-Slope Roofing17%
  • Job Site Preparation13%

Section weights from the official exam outline. Bigger sections are worth more points, so study them first.

A 4-step study plan

  1. Take a baseline test. Answer a full mock exam before studying so you know where you stand in each section.
  2. Study by weight, then by weakness. Start with Steep-Slope Roofing (26%), Planning & Estimating (22%), Safety (22%), then move to whichever sections scored lowest on your baseline.
  3. Learn the rule, not just the answer. For every miss, read the explanation and the code section or statute it cites; on test day you'll need to know these references well.
  4. Repeat mock exams until you're consistently at 80% or more, which gives you a cushion above the passing score. Retake the questions you missed until they stick.

Key rules to know, by section

A few of the facts that come up in each section, with the answer and the source. The full course has 1,353 questions with explanations.

Steep-Slope Roofing 26% of the exam · 56 practice questions

  • Shingle nails must penetrate the roof sheathing at least? 3/4 in or through the sheathing. Rule (CRC §R905.2.5): asphalt shingle fasteners must be corrosion-resistant roofing nails long enough to penetrate through the roofing and at least 3/4 inch into the sheathing, or all the way through sheathing thinner than 3/4 inch. Calif. Residential Code §R905.2.5 (shingle fasteners) ↗
  • A kickout (diverter) flashing is installed? Where a roof edge ends at a sidewall, to direct water into the gutter. Rule (CRC §R903.2.1): a flashing must be installed to divert water away from where the eave of a sloped roof meets a vertical sidewall. This kick-out flashing directs water into the gutter instead of behind the siding. Calif. Residential Code §R903.2.1 (flashing locations, kick-out) ↗
  • Granule loss on asphalt shingles indicates? Aging or damage that exposes the asphalt to UV. Granules protect the asphalt from UV and give shingles their color. Heavy granule loss (granules in gutters, bare spots) means the shingles are aging or damaged, and exposed asphalt will deteriorate quickly.

Planning & Estimating 22% of the exam · 17 practice questions

  • Reroofing in California climate zones with cool roof requirements may require? Roofing products meeting Title 24 aged solar reflectance and emittance. Rule (California Energy Code §150.2(b)1I): when more than half of a steep or low-slope roof is replaced in certain climate zones, the new roofing products must meet minimum aged solar reflectance and thermal emittance (cool roof) values, with listed exceptions. Calif. Energy Code §150.2(b)1I (reroofing — aged solar reflectance) ↗
  • Hips and ridges are estimated in? Linear feet for cap shingles. Hip and ridge cap shingles are estimated in linear feet of hips and ridges, then converted to bundles using the cap product's coverage per bundle.
  • Overhead and profit on a roofing bid are added to? Total direct cost (materials, labor, equipment, disposal). Overhead and profit are added on top of the total direct cost of the job: materials, labor, equipment, permits and disposal. Leaving out a direct cost means the markup is calculated on too small a number.

Safety 22% of the exam · 44 practice questions

  • Ladders should be set up at a slope of? 4:1. Rule (Cal/OSHA Title 8 §3276): set a straight or extension ladder at a 4:1 slope: the base 1 foot out for every 4 feet of height to the top support, about 75 degrees. Cal/OSHA Title 8 §3276 (portable ladders) ↗
  • Pneumatic nailers on roofs should? Be used with safeties working and hoses managed to prevent trips. Use pneumatic nailers with their safety contact working (never disabled), keep fingers clear, and manage hoses so they don't become trip hazards. Nail gun injuries are common on roofs.
  • Fire extinguishers on roofing jobs using torches or kettles should be? Within easy reach of the hot work. Where torches or kettles are used, keep a suitable charged fire extinguisher within easy reach of the hot work, so a fire can be put out before it spreads.

Low-Slope Roofing 17% of the exam · 44 practice questions

  • Roofs with parapets that could trap water need? Secondary (overflow) drains or scuppers. Rule (CRC §R903.4.1): where roof drains are required and the roof perimeter extends above the roof so water could be trapped (such as parapets), secondary emergency overflow drains or scuppers must be provided. Calif. Residential Code §R903.4.1 (secondary drains or scuppers) ↗
  • Low-slope membranes should be lapped so that? Water flows over laps, not into them (shingle fashion). Lap membranes shingle fashion, starting at the low point (drains or eaves) and working upslope, so water flows over the laps instead of into them.
  • Expansion joints on low-slope roofs are installed? Where the structure has building expansion joints. Roof expansion joints are installed wherever the building structure has expansion joints (and where deck direction or material changes), so the roof can move with the building without tearing the membrane.

Job Site Preparation 13% of the exam · 27 practice questions

  • Panel edge clips (H-clips) on roof sheathing are used to? Support unblocked panel edges between rafters. Panel edge clips (H-clips) support the unblocked long edges of roof sheathing panels between rafters or trusses. They keep adjacent edges level and reduce deflection when there is no blocking.
  • Roof sheathing gaps wider than allowed in spaced sheathing under shingles must be? Covered with solid sheathing before installing shingles. Rule (CRC §R905.2.1): asphalt shingles must be fastened to solid sheathing (wood structural panels or solid lumber). Where shingles go over existing spaced sheathing, the gaps must be covered with solid sheathing first. Calif. Residential Code §R905.2.1 (asphalt shingle sheathing) ↗
  • After tear-off, the yard should be swept for nails using? A magnetic sweeper. After tear-off, sweep the yard, driveway and walkways with a magnetic sweeper (several times) to pick up loose roofing nails that injure people and puncture tires.

The Law & Business exam

Most California applicants also take the Law & Business exam. Its sections:

  • Contracts21%
  • Employment20%
  • Business finances15%
  • Safety14%
  • Licensing13%
  • Insurance & liens12%
  • Public works5%

Contracts 21% of the exam · 257 practice questions

  • A homeowner under 65 who signs a home improvement contract at home can cancel within? 3 business days. Rule (Civil Code §1689.6 and §7159): a buyer who signs a home improvement contract at home generally has 3 business days to cancel; the contract must include the Three-Day Right to Cancel notice. Seniors 65 and older get 5 business days. Civil Code §1689.6 (3-day right to cancel) ↗
  • Statute of limitations to sue on a written contract in California? 4 years. Rule (Code of Civil Procedure §337): a lawsuit for breach of a written contract must be filed within 4 years after the breach. Oral contracts have a shorter 2-year limit (CCP §339). Code of Civil Procedure §337 (written contracts) ↗

Employment 20% of the exam · 241 practice questions

  • An employee quits without notice. Final wages are due within? 72 hours. Rule (Labor Code §202): an employee who quits without giving at least 72 hours' notice must be paid within 72 hours. If the employee gave 72 hours' notice or more, final wages are due on the last day of work. Labor Code §202 (final pay within 72 hours) ↗
  • Each paycheck must include? An itemized wage statement. Rule (Labor Code §226): with each paycheck, employers must give an itemized wage statement showing gross wages, total hours worked, all deductions, net wages, the pay period dates, the employee's name and last 4 digits of the SSN or an ID number, the employer's name and address, and all hourly rates with hours at each rate. Labor Code §226 (itemized wage statement) ↗

Business finances 15% of the exam · 147 practice questions

  • Which statement shows the business's financial position at one point in time? Balance sheet. The balance sheet is a snapshot on one date. It lists what the business owns (assets), what it owes (liabilities) and the owners' equity, and it always balances: assets = liabilities + equity.
  • The sales volume where revenue exactly covers all costs is the? Break-even point. The break-even point is the sales volume at which total revenue equals total costs (fixed plus variable), so profit is zero. Above break-even each sale adds profit; below it the business loses money.

Safety 14% of the exam · 158 practice questions

  • Information on hazards of a chemical product is found on its? Safety Data Sheet (SDS). Rule (Title 8 §5194, Hazard Communication): manufacturers must provide a Safety Data Sheet (SDS) for every hazardous chemical, and employers must keep SDSs readily accessible to workers on each shift. Cal/OSHA Title 8 §5194 (Hazard Communication, safety data sheets) ↗
  • When a ladder is used to reach an upper landing, its side rails must extend at least how far above the landing? 3 feet. Rule (29 CFR §1926.1053(b)(1); Cal/OSHA has the same rule): portable ladder side rails must extend at least 3 feet above the upper landing, or the ladder must be secured with a grab rail, so the worker has a handhold getting on and off. 29 CFR §1926.1053 (ladder 3 ft above landing) ↗

Licensing 13% of the exam · 152 practice questions

  • An expired license can be renewed (without reapplying) for up to how long after it expires? 5 years. Rule (B&P §7141): an expired (delinquent) license can be renewed within 5 years after it expires by paying the renewal and delinquency fees. After 5 years it cannot be renewed and the business must apply for a new license, including any required exams. Bus. & Prof. Code §7141 (renewal within five years) ↗
  • A lawsuit for a latent (hidden) construction defect must generally be filed within how many years of substantial completion? 10 years. Rule (Code of Civil Procedure §337.15): a lawsuit for a latent (hidden) construction defect must be filed within 10 years after substantial completion. Patent (obvious) defects fall under the shorter 4-year limit in CCP §337.1. Code of Civil Procedure §337.15 (10 years for latent defects) ↗

Insurance & liens 12% of the exam · 145 practice questions

  • An owner must record a notice of completion within how many days after completion? 15. Rule (Civil Code §8182): an owner's notice of completion must be recorded within 15 days after completion of the work of improvement; a notice recorded later is not valid, and the longer 90-day lien periods then apply. Civil Code §8182 (notice of completion) ↗
  • After receiving a progress payment, a prime contractor must pay its subcontractors within? 7 days. Rule (B&P §7108.5): a prime contractor must pay each subcontractor its share of a progress payment within 7 days after receiving it, unless the parties agreed otherwise in writing. Late payment carries a penalty of 2% per month on the amount due. Bus. & Prof. Code §7108.5 (prompt payment to subs) ↗

Public works 5% of the exam · 65 practice questions

  • A public works payment bond is required when the contract exceeds? $25,000. Rule (Civil Code §9550): a direct contractor awarded a public works contract over $25,000 must give the public entity a payment bond before work starts, guaranteeing payment to subcontractors, laborers and suppliers. Civil Code §9550 (public works payment bond) ↗
  • The annual DIR public works contractor registration fee is? $400. Rule (Labor Code §1725.5): contractors and subcontractors must register with the Department of Industrial Relations before bidding on or performing public works, and pay an annual registration fee — currently $400 — renewed every year (or up to three years at once). Labor Code §1725.5 (DIR registration) ↗

Questions people ask

What is on the California C-39 Roofing exam?

The exam is weighted by section: Steep-Slope Roofing 26%, Planning & Estimating 22%, Safety 22%, Low-Slope Roofing 17%, Job Site Preparation 13%.

What is the format of the California C-39 Roofing exam?

Computer-based, multiple choice with four answer choices and one best answer. 3½ hours for each exam, trade and Law & Business (CSLB exam FAQ). CSLB does not publish the number of questions or the passing score. Closed book: no reference materials; a calculator is provided. Most applicants also take the Law & Business exam (included free with every trade exam here).

What should I study first for the California C-39 Roofing exam?

Start with the largest sections, which carry the most points: Steep-Slope Roofing (26%), Planning & Estimating (22%), Safety (22%). Then take a timed mock exam and spend extra time on whatever scored lowest.

Do I also need the Law & Business exam?

Most applicants for this license also take the Law & Business exam. It is included with this course, so you can practice both.

Where can I practice for the California C-39 Roofing exam?

LicenseExamReady has 1,353 practice questions for the California C-39 Roofing exam and the Law & Business exam, full mock exams weighted like the real test, explanations that cite the code section or rule, and a readiness score. New accounts get a free 3-day trial.

Are practice questions the same as the real exam?

No. Licensing boards keep their exams confidential. Good practice questions are written from the official exam outline and code books and teach the rule behind each answer.

Practice for the California C-39 Roofing exam

1,353 practice questions, full-length timed mock exams weighted like the real test, explanations with sources, and a readiness score that shows when you're ready to book the exam.